Pellet-Sinter Composite Agglomerate of Iron Oxide Fines for Use in Blast Furnace
1. |
Title of Product/Design/Equipment |
Pellet-Sinter Composite Agglomerate of Iron Oxide Fines for Use in Blast Furnace |
|
2. |
IPR Status Patent/Abroad IPR Details |
Patent Filed |
|
3. |
Application/Uses |
Iron and steel making |
|
4. |
Salient Technical Features including Competing Features |
In Pellet-Sinter Composite Agglomerate, iron oxide pellets are embedded in to the sinter mass. P-SCA for use in blast furnace has been developed with Indian iron ore to utilize the micro-fines in sintering. The salient features of the process are as follows: It also uses steel plant's waste materials viz. LD sludge, mill scale etc (5-10%) with iron oxide microfines. The process yields a very good quality sinter even at the lower basicity that is usable in blast furnace. It increases the fines acceptability (30% above normal) improving permeability and decreases energy consumption (-20%) and flux consumption. |
|
5. |
Level/Scale of Development |
12 kg / batch |
|
6. |
Environmental Considerations |
Environment friendly since it reduces Energy consumption No harmful/hazardous effect on environment |
|
7. |
Status of Commercialization |
Ready for commercialization |
|
8. |
Major Raw Materials to be Utilized |
Iron ore fines, LD Sludge, BF-Blue Dust. |
|
9. |
Major Plant Equipment and Machinery Required |
Pelletizer, Conventional sintering facility, charging system |
|
10. |
Techno-Economics |
Present sinter strand in steel plant can be used for Up-scaling. Only a pelletizer of suitable capacity with charging facility has to be installed.Raw materials are fines and wastes. |
|
11. |
Technology Package |
(a) Process-Know-how, (b) Details of equipment & (c) Quality Assurance Methods. Assistance in up-scaling and setting up the plant on separate terms. |
Chemical requirement cost is about Rs.30.10 against product cost of about Rs.1.25.10 per ton of iron oxide production.